Commercial Building - New & Addition
Applicable Codes:
2024 International Building Code
2024 International Mechanical Code
2024 International Fire Code
2024 International Plumbing Code
2014 Illinois Plumbing Code
Illinois Energy Code (current edition)
2023 National Electrical Code
Please submit the following information:
- Site Development
- Site development drawings that comply with Grading Plan Requirements Type III, that depict full scope of work.
- Utility Permit Application for all new commercial buildings/additions (if applicable).
- DuPage County Impact Fee Receipt (only for new commercial buildings).
- Wheaton Sanitary District or DuPage County sanitary permit.
- Sewer permit (if new construction).
- DuPage County Stormwater Management info & completed type 3 stormwater checklist.
- Water service line sizing PDF uploaded Water Service Line - Sizing. Questions regarding Commercial Load Value calculations should be directed to the Water Division at 630-260-2090.
- Building Construction
- Signed and sealed building construction plans.
- Signed and sealed project manual.
- Signed and sealed set of structural calculations.
- Signed and sealed soil report.
- Signed and sealed ComCheck. Include lighting/mechanical/exterior lighting and envelope.
- New Commercial Building Code Analysis (only for new commercial buildings).
Significant Code Requirements
- Zoning Requirements - See City of Wheaton Zoning Ordinance.
- Construction Site Regulations - For job site regulations such as hours of work, safety fencing, parking of construction vehicles, and similar, see the guideline titled Demolition and Construction Regulations.
Inspections
The inspections listed here are required for all new commercial buildings and addition projects. Additional inspections may be needed based on the scope of work for your project. A complete list of your required inspections will be listed on the Plan Approval Notice that will be attached to the approved plans.
| Type of Inspection |
|---|
| Footing |
| Foundation Wall |
| A Top of Foundation Survey must be submitted before Backfill |
| Backfill (for new buildings and additions with basements only) |
| Electrical Service (if applicable) |
| Water Service (if applicable) |
| Underground Electrical/Plumbing (if applicable) |
| Rough Inspections (Framing, Electrical, Mechanical, Plumbing) |
| Above-Ceiling Inspections (electrical/mechanical/plumbing/fire alarm/fire sprinkler) |
| Fire Alarm |
| Insulation |
| Masonry Firebox (if applicable) |
| Exterior Masonry (if applicable) |
| Final Grading Survey must be submitted |
| Final Inspections (Building, Plumbing, Fire, Engineering) |
To schedule an inspection
Please call 630-260-2050 between 8:00 a.m. and 5:00 p.m. Monday through Friday. Please allow for a minimum of 24 hours' notice when scheduling inspections. Inspections must be scheduled no later than 3:00 p.m. the day before the desired inspection date. Inspection Scheduling Guideline.
To apply for a permit
Maintstar - h2.maintstar.co/wheaton/portal/#/
Contractor Registration Requirements
Webpage - www.wheaton.il.us/890/Contractor-Registration-Requirements
Contact Us
City of Wheaton Building & Code Enforcement Department
Address: 303 W. Wesley Street, Wheaton, IL 60187
Phone Calls:
Questions regarding this information: 630-260-2050
Business hours: Monday-Friday 8:00 a.m. - 5:00 p.m.
Fax: 630-260-2195
12/15/2025