Downtown Wheaton Streetscape

The City of Wheaton Downtown Streetscape is a multi-year infrastructure project bringing updates and improvements to underground utilities, roadways, lighting and signage while creating wider, more pedestrian-friendly sidewalks throughout downtown Wheaton. Downtown Streetscape Map & Timeline

  • Year 1 - Fall 2017 thru Fall 2018 - Front Street from West to Cross Street
  • Year 2 - Fall 2018 thru Summer 2019 - Hale Street from Willow to Seminary; Wesley from Wheaton Avenue to Cross Street; and Cross Street from Front to Wesley Street
  • Year 3 - Fall 2019 thru Summer 2020 - Liberty Drive from West to Hale Street, Main Street from Illinois to Wesley Street, and Wheaton Avenue from Liberty to Wesley Street.
  • Year 4 - Fall 2020 thru Summer 2021 - Cross Street from Liberty Drive to Front StreetLiberty Drive from Hale to Cross Street & Parking Lot #4

Wesley/Hale/Cross - In Progress

Streets: Wesley from Wheaton Avenue to Cross Street; Hale Street from Willow Avenue to Seminary; Cross from Front to Wesley Street
Start date: September 2018
Completion date: October 31, 2018
Times: M-F & select Saturdays / 7am-dusk

John Neri Construction Company, Inc. is currently replacing aging water main and sanitary sewers on Wesley, Hale and Cross Street.

Sidewalk, roadway, lighting, landscaping and signage improvements will begin in late Spring 2019.

For questions and more information on this project, please call the Engineering Department at 630-260-2065.

Front Street Streetscape - In Progress

Streets: Front Street from West to Cross Street
Start date: April 2018
Completion date: Fall 2018
Times: M-F & select Saturdays / 7am-dusk

Landmark Construction has replaced the roadways and curbs, created wider sidewalks and an amenity zone and will be adding new lighting, benches, and landscaping beds. Martin Memorial Plaza has been relocated to the north side of Front Street. The new plaza will contain a new water feature and an outdoor fireplace.

Front Street Underground Utility Improvements

Streets: Front Street from West to Cross Street
Start date: September 2017
Completion date: November 2017

Copenhaver Construction has replaced aging water main and sanitary sewers on Front Street from West to Cross Street.

For questions and more information on this project, please call the Engineering Department at 630-260-2065.

Downtown Wheaton Strategic Plan & Streetscape Plan – Planning Phase 2

Start Date: Winter 2016
Completion Date: Summer 2016
Estimated Cost: $177,740
Contact: Director of Planning, James P. Kozik

Related Information

Following completion and adoption of the Downtown Strategic Plan and Streetscape Plan in February 2014, the City Council desired to engage the design services of a streetscape/engineering professional to assist the City with the implementing and construction of the public infrastructure elements identified in the Downtown Strategic and Streetscape Plan.

The City conducted a request for qualifications and request for proposal process and received and reviewed eight submittals for streetscape/engineering professional design services and determined that the proposal received from Design Workshop met the City’s needs for this project.

The following tasks are associated with completing this project:

  • Project kickoff and work session 
  • Programming
  • Concept Design
  • Stakeholder Engagement
  • Final Concepts and Presentation

The complete design services agreement can be seen in the City Council Resolution below. As this project progresses, this page and the following links will be updated.

Planning Phase 2 Documents

Downtown Wheaton Strategic Plan & Streetscape Plan – Planning Phase 1

Phase: Plan completed
Completion Date: Completed; approved by City Council February 2014
Estimated Cost: $150,000
Contact: Director of Planning, James P. Kozik

View the final Downtown Wheaton Strategic Plan and Streetscape Plan (PDF).

Related Information

One of the Wheaton City Council's goals in their 2014 Strategic Priorities was economic development in the City's downtown. A key part of that will be the development of a Downtown Wheaton Strategic Plan and a Downtown Streetscape Plan.

Planning Phase 1 Documents